M&C Review


COUNCIL ACTION:  Approved on 11/3/2009 - Ord. No. 18899-11-2009

DATE: 11/3/2009 REFERENCE NO.: C-23896 LOG NAME: 60WSO2STMO-RODGERS
CODE: C TYPE: NON-CONSENT PUBLIC HEARING: NO
SUBJECT:   Authorize a Contract in the Amount of $1,280,510.20 with Rodgers Construction Company for Water and Sanitary Sewer Replacement Contract 2002, STM-O on South Hills Avenue, West Spurgeon Street, Townsend Drive, Westcrest Drive and West Fuller Street and Adopt Appropriation Ordinance

RECOMMENDATION:

It is recommended that the City Council:
  
1. Authorize the transfer of $1,379,087.00 from the Water and Sewer Operating Fund to the Water Capital Projects Fund in the amount of $935,642.00 and Sewer Capital Projects Fund in the amount of $443,445.00;
  
2. Adopt the attached appropriation ordinance increasing estimated receipts and appropriations in the Water Capital Projects Fund by $935,642.00 and in the Sewer Capital Projects Fund in the amount of $443,445.00; and
  
3. Authorize the City Manager to execute a contract in the amount of $1,280,510.20 with Rodgers Construction Company for Water and Sanitary Sewer Replacement Contract 2002, STM-O.

 
DISCUSSION:

On August 12, 2003, (M&C C-19700) the City Council authorized an Engineering Agreement with A.N.A. Consultants, L.L.C., for preparation of plans and specifications for Water and Sanitary Sewer Replacements Contract 2002, STM-O. (Project 00326)
  
The project provides for the replacement of the deteriorated water and sanitary sewer mains as indicated on the following streets:

Street

From

To

Scope of Work

South Hills AvenueUniversity DriveTrail Lake DriveWater/Sewer
West Spurgeon StreetHemphill StreetCollege AvenueWater/Sewer
Townsend DriveWest Spurgeon StreetYates StreetWater
Westcrest DriveWayside AvenueEdgecliff  RoadWater/Sewer
West Fuller StreetMcCart AvenueGordon AvenueWater
  
After the proposed improvements are complete and under a separate contract all the identified roadways will be overlayed with asphalt.
  
The project was advertised for bid on July 16, 2009, and July 23, 2009, in the Fort Worth Star-Telegram. On August 13, 2009, the following bids were received:
  
  
  

Bidder

Amount

Time of Completion

Rodgers Construction Company

$1,280,510.20

180 Calendar Days

Texas United Excavation, Inc.

$1,342,320.00

Burnsco Construction, Inc.

$1,381,896.40

Tri Tech Construction, Inc.

$1,388,571.00

S.H.U.C, Inc.

$1,412,620.00

Conatser Construction, Inc.

$1,462,365.00

RKM Utilities

$1,468,869.40

M.E. Burns Construction, Inc.

$1,473,602.25

Jackson Construction, Inc.

$1,545,636.75

Gra Tex Utilities

$1,564,810.25

SLC Construction

$1,629,817.24

Barson Utilities

$1,641,052.75

Municipal Utilities

$1,647,898.00

  
In addition to the contract cost, $52,000.00 (Water: $37,000.00 and Sewer: $15,000.00) is required for construction staking, inspection and material testing and $46,576.80 (Water: $26,174.04 and Sewer: $20,402.76) is provided for project contingencies.
  
Rodgers Construction Company is in compliance with the City's M/WBE Ordinance by committing to 24 percent M/WBE participation. The City's goal on the project is 15 percent.
  
The project is located in COUNCIL DISTRICT 9.
  

 
FISCAL INFORMATION/CERTIFICATION:

The Financial Management Services Director certifies that upon approval of the above recommendations, and adoption of the attached appropriation ordinance, funds will be available in the current capital budgets, as appropriated, of the Water Capital Projects Fund and the Sewer Capital Projects Fund.

 
TO Fund/Account/Centers
1&2) P258  476045  7091700326ZZ   $443,445.00
1&2) P253  476045  6091700326ZZ   $935,642.00
2) P253  531350  609170032652   $8,000.00
2) P253  531200  609170032684   $8,000.00
2) P253  531350  609170032684   $4,000.00
2) P253  541200  609170032683   $898,642.00
2) P253  531350  609170032685   $15,000.00
2) P253  511010  609170032682   $2,000.00
2) P258  531350  709170032652   $4,000.00
2) P258  531200  709170032684   $2,000.00
2) P258  531350  709170032684   $1,000.00
2) P258  541200  709170032683   $428,445.00
2) P258  531350  709170032685   $7,000.00
2) P258  511010  709170032680   $1,000.00
 
FROM Fund/Account/Centers
1) PE45  538040  0609020   $935,642.00
1) PE45  538040  0709020   $443,445.00
3) P253  541200  609170032683   $872,467.96
3) P258  541200  709170032683   $408,042.24

Submitted for City Manager's Office by:
Fernando Costa (6122)
Originating Department Head:
S. Frank Crumb (8207)
Additional Information Contact:
Rakesh Chaubey (6051)

 
 
ATTACHMENTS
  60WS02STMO-RODGERS MAP 1.pdf
  60WS02STMO-RODGERS MAP 2.pdf
  60WS02STMO-RODGERS MAP 3.pdf
  60WS02STMO-RODGERS MAP 4.pdf
  60WSO2STMO-RODGERS AO.doc