Authorize a Contract in the Amount of $1,758,144.40 with Burnsco Construction, Inc., for Sanitary Sewer Rehabilitation Contract LXX, Part 4, on Monticello Drive, Potomac Avenue, Williamsburg Lane, West Jarvis Street and Two Alleyways and Adopt Appropriation Ordinance

RECOMMENDATION:

It is recommended that the City Council:
  
1. Authorize the transfer of $1,838,945.00 from the Water and Sewer Fund to the Water Capital Projects Fund in the amount of $731,221.00 and the Sewer Capital Projects Fund in the amount of $1,107,724.00;
  
2. Adopt the attached appropriation ordinance increasing estimated receipts and appropriations in the Water Capital Projects Fund by $731,221.00 and  the Sewer Capital Projects Fund in the amount of $1,107,724.00; and
  
3. Authorize the City Manager to execute a contract with Burnsco Construction, Inc., in the amount of $1,758,144.40 for Sanitary Sewer Rehabilitation Contract LXX, Part 4.

 
DISCUSSION:
On March 23, 2004, (M&C C-20000) the City Council authorized an engineering agreement with Kimley-Horn & Associates, Inc. for Sanitary Sewer Rehabilitation Contract LXX (70).
  
This project provides for the replacement of the deteriorated water and sanitary sewer mains as indicated on the following streets and alleyways:
  
StreetFromTo

Scope of Work

Monticello DriveRivercrest DriveHamilton Avenue

Water

Potomac AvenueVirginia Place       Fourth Street

Water

Williamsburg LaneBristol RoadBailey Avenue

Water

West Jarvis StreetSouth Adams StreetLipscomb Street

Sewer

Montgomery StreetLinden AvenueByers Avenue

Sewer

Alleyway Between Hillcrest

El Campo AvenueBryce Avenue

Sewer

   Street and Thomas Place
Alleyway Between FourthMonticello DriveBoland Street

Sewer

    Street and Hamilton Avenue
  
The project was advertised for bid on June 18, 2009, and June 25, 2009, in the Fort Worth Star-Telegram. On August 13, 2009, the following bids were received:
  
  
  
  
  
Bidders
Bid Amount
Time of Completion
Texas United Excavators, LLC*
$1,723,058.50
240 Calendar Days
Burnsco Construction, Inc.
$1,758,144.40
Barson Utilities, Inc.
$1,982,268.25
Conatser Construction TX, LP

$1,986,343.50

SLC Construction, LLC
$2,065,135.04
      
*The apparent low bidder Texas United Excavators, LLC, (TUE) has been determined by staff to be non-responsive to the contract specifications due to failure to comply with the prequalification pipe size restriction. TUE is prequalified to only install water and/or sanitary sewer mains 12 inches in diameter and smaller. This project includes 370 linear feet of 18 inch diameter sewer pipe.
  
In addition to the contract amount $24,000.00 (Water: $8,000.00 and Sewer: $16,000.00) is required for material testing and inspection and $56,800.60 (Water: $25,000.00 and Sewer: $31,800.60) is provided for change order contingencies.
  
M/WBE - Burnsco Construction, Inc., is in compliance with the City's M/WBE Ordinance by committing to nine percent M/WBE participation and documenting good faith. Burnsco Construction, Inc., identified several subcontracting and supplier opportunities. However, the M/WBE contacted in the areas identified did not submit the lowest bids. The City's goal on this project is 22 percent.
  
This project is located in COUNCIL DISTRICT 7.
 
FISCAL INFORMATION/CERTIFICATION:

The Financial Management Services Director certifies that upon approval of the above recommendations and adoption of the attached appropriation ordinance funds will be available in the current capital budget, as appropriated, of the Water Capital Projects Fund and the Sewer Capital Projects Fund.

 
TO Fund/Account/Centers
1&2) P253  476045  6091700439ZZ   $731,221.00
1&2) P258  476045  7091700439ZZ   $1,107,724.00
2) P253  511010  609170043980   $4,000.00
2) P253  531200  609170043984   $4,000.00
2) P253  541200  609170043987   $723,221.00
2) P258  511010  709170043980   $8,000.00
2) P258  531200  709170043984   $8,000.00
2) P258  541200  709170043987   $1,091,724.00
 
FROM Fund/Account/Centers
1) PE45  538040  0609020   $731,221.00
1) PE45  538040  0709020   $1,107,724.00
3) P253  541200  609170043987   $698,221.00
3) P258  541200  709170043987   $1,059,923.40

Submitted for City Manager's Office by:
Fernando Costa (8476)
Originating Department Head:
Frank Crumb (8207)
Additional Information Contact:
Liam Conlon (6824)

 
 
ATTACHMENTS
  60SS70P4-BURNSCO AO.doc
  60SS70P4-BURNSCO MAP 1.pdf
  60SS70P4-BURNSCO MAP 2.pdf
  60SS70P4-BURNSCO MAP 3.pdf