M&C Review


COUNCIL ACTION:  Approved on 11/3/2009 - Ord. No. 18898-11-2009

DATE: 11/3/2009 REFERENCE NO.: C-23895 LOG NAME: 60SSVCP4-CONATSER
CODE: C TYPE: NON-CONSENT PUBLIC HEARING: NO
SUBJECT:   Authorize a Contract in the Amount of $928,536.50 with Conatser Construction TX, LP, for Village Creek Drainage Basin Sanitary Sewer System Rehabilitation, Part 4, on Cravens Road, John T. White Road, Hardeman Street, Rosedale Street and Tension Drive and Adopt Appropriation Ordinance

RECOMMENDATION:

It is recommended that the City Council:

1. Authorize the transfer of $213,283.00 from the Water and Sewer Operating Fund to the Sewer Capital Projects Fund;

2. Adopt the attached appropriation ordinance increasing estimated receipts and appropriations in the Sewer Capital Projects Fund in the amount of $213,283.00 from available funds; and

3. Authorize the City Manager to execute a contract with Conatser Construction TX, LP, in the amount of $928,536.50 for Village Creek Drainage Basin Sanitary Sewer System Rehabilitation, Part 4.

 
DISCUSSION:

On July 30, 2002, (M&C C-19172) the City Council authorized the City Manager to execute an Engineering Agreement with Dannenbaum Engineering, Inc., for the preparation of plans and specifications for Sanitary Sewer Main Nos. 257 and 325 Middle and Upper Village Creek Parallel Relief Alignment Study and Design.

This project, Village Creek Drainage Basin Sanitary Sewer System Rehabilitation, Part 4, Units 1 and 2, consists of the construction of approximately 5,670 feet of sewer, within the following streets:

Street

From

To

Cravens Road

Maceo Lane

Tallie Road

John T. White Road

Morrison Lane

362 Feet East

Hardeman Street

Erath Street

Nolan Street

Rosedale Street

Ransom Terrace

Tension Drive

Tension Drive

At T&P Railroad Crossing

The project was advertised for bid on June 25, 2009, and July 2, 2009, in the Fort Worth Star-Telegram. On July 23, 2009, the following bids were received:

Bidder

Amount

Time of Completion

Conatser Construction TX, LP

$928,536.50

150 Calendar Days

William J. Schultz, Inc.,

$1,050,355.00

   d/b/a Circle "C" Construction Company

Jackson Construction

$1,059,777.50

AUI Contractors, Inc.

$1,064,628.50

Rogers Construction Company

$1,270,906.25

The project was bid as two units. Unit 1 consists of all project elements that were determined by the Texas Water Development Board (TWDB) to be eligible for funding with Clean Water State Revolving Funds (CWSRF). The bid amount for Unit 1 was $764,453.50. Unit 2 consists of those project elements which were determined not to be eligible for CWSRF. The bid amount for Unit 2 was $164,083.00.

M/WBE - Conatser Construction TX, LP, is in compliance with the City's M/WBE Ordinance by committing to 19 percent M/WBE participation. The City's goal on this project is 18 percent.

Most State Revolving Loans are granted for construction contracts only. However with this particular loan the City of Fort Worth was authorized to pay for both an Engineering Agreement (design and survey) and the Construction Contract. Since no other expenses can be covered by SRF funding, additional appropriations of $49,200.00 ($41,000.00 for construction staking, project management material testing and inspection and $8,200.00 for project contingencies) are needed from the Sewer Capital Projects Fund.

The project is located in COUNCIL DISTRICTS 4 and 5.

 
FISCAL INFORMATION/CERTIFICATION:

The Financial Management Services Director certifies that upon approval of the above recommendations and adoption of the attached appropriation ordinance, funds will be available in the current capital budgets, as appropriated, of the Sewer Capital Projects Fund and the Clean Water State Revolving Loan Fund 2007.

 
TO Fund/Account/Centers
1&2) P258  476045  7041701054ZZ   $213,283.00
2) P258  531350  704170105452   $10,000.00
2) P258  511010  704170105480   $3,000.00
2) P258  541200  704170105489   $172,283.00
2) P258  531200  704170105484   $5,000.00
2) P258  531350  704170105484   $3,000.00
2) P258  531350  704170105485   $20,000.00
 
FROM Fund/Account/Centers
1) PE45  538040  0709020   $213,283.00
3) P254  541200  704170105489   $764,453.50
3) P258  541200  704170105489   $164,083.00

Submitted for City Manager's Office by:
Fernando Costa (6122)
Originating Department Head:
S. Frank Crumb (8207)
Additional Information Contact:
David Cooper (8252)

 
 