Types of Wells:

Less than 600 feet Gas Well Permit is required if the proposed well is to be located within six hundred (600) feet of a residence, religious institution, hospital building, school or public park.

More than 600 feet Gas Well Permit is required if the proposed well is to be located more than six hundred (600) feet of a residence, religious institution, hospital building, school or public park.

 

Stages of Gas Well Drilling Production

gas well pic

 

Stage 1

WELL SITE SURVEYED AND STAKED

Duration: 1-6 months

rig site prep

Stage 2

WELL SITE BEING PREPARED FOR RIG SETUP

Duration: 1-3 weeks

rig at location

Stage 3

RIG SET UP AT LOCATION FOR 30 DAYS

Duration: 30 days

tank site

Stage 4

TANK SITE BEFORE LANDSCAPING IS COMPLETED

Duration: 4-12 months