Types of Wells:
Less than 600 feet Gas Well Permit is required if the proposed well is to be located within six hundred (600) feet of a residence, religious institution, hospital building, school or public park.
More than 600 feet Gas Well Permit is required if the proposed well is to be located more than six hundred (600) feet of a residence, religious institution, hospital building, school or public park.
Stages of Gas Well Drilling Production
![]() |
Stage 1 WELL SITE SURVEYED AND STAKED Duration: 1-6 months |
![]() |
Stage 2 WELL SITE BEING PREPARED FOR RIG SETUP Duration: 1-3 weeks |
![]() |
Stage 3 RIG SET UP AT LOCATION FOR 30 DAYS Duration: 30 days |
![]() |
Stage 4 TANK SITE BEFORE LANDSCAPING IS COMPLETED Duration: 4-12 months |